6. Key Milestone Summary

This section responds to the Title 10, U.S. Code, section 2222, requirement to report specific milestones and actual performance against specified performance measures and any revision of milestones and performance measures. During FY08, the Department met 182 of 299 scheduled milestones. Additionally, the Department met 57% of its FY08 retirement targets, retiring 12 of the 21 legacy systems. Table 6-2 displays milestone performance for FY08 and includes a specific explanation for each unmet milestone. The status column in Table 6-2 indicates whether each unmet milestone was slipped, deleted or corrected for administrative reasons.

Only 16% (49/299) of the Department’s milestones were not accomplished within their scheduled timeframe. These milestones are labeled “slipped” in the status column of Table 6-2. A single slipped milestone can create a domino effect of milestone slippages within a program. These program intra-dependencies account for 20 of the 49 total slipped milestones, as shown in Table 6-1. For example, the Defense Integrated Military Human Resources System (DIMHRS) did not meet its System Acceptance Testing milestone, which cascaded into six other slipped milestones within the DIMHRS program.

Table 6-1: Accounting for Slipped Milestones

Programs Slipped Milestones

Defense Integrated Military Human Resources System

7

USAF Personnel Service Delivery

7

Navy Enterprise Resource Planning

2

Navy Total Force Structure Management System

2

Defense Enterprise Accounting and Management System-Air Force

2

Total

20

 

Additionally, 68 milestones were “deleted.” Continually honing the alignment of program direction to the Enterprise’s or Component’s priorities accounted for 44 of the 68 deleted milestones. For instance, as the Components implemented RPIR, it became clear that separate milestones for different data element groupings within RPIR were not required. This change resulted in the deletion of ten milestones. A wide variety of unique reasons account for the remaining 24 deleted milestones.

Milestones corrected for administrative reasons, such as duplicate or mislabeled milestones, were not included in the overall total number of 299 milestones.

Table 6-2 displays the milestones scheduled for completion during FY08, as provided by the September 2007 ETP and the March 2008 Congressional Report.


Table 6-2: FY08 Key Milestone Summary

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Personnel Visibility

DCPDS  Defense Civilian Personnel Data System

 

 

 

 

Define high level technical and functional requirements for HR/Payroll and conduct Preliminary Requirements Review

 

2/2008

 Deleted

No FY08 project funding has been provided for the HR/Payroll

Develop Preliminary Design for the HR/Payroll initiative and conduct preliminary Design Review

 

4/2008

 Deleted

No FY08 project funding has been provided for the HR/Payroll

Final Requirements Review

 

5/2008

 Deleted

No FY08 project funding has been provided for the HR/Payroll

Complete the translation of HR/Payroll into a detailed design and conduct Critical Design Review

 

6/2008

 Deleted

No FY08 project funding has been provided for the HR/Payroll

DIMHRS  Defense Integrated Military Human Resources System

 

 

 

 

Increment: Army

 

 

 

 

System Integration Test

8/2008

2/2008

Met

 

System Acceptance Test

TBD

3/2008

 Slipped

Critical Change Report submitted Jan 31, 2009

Operational Test and Evaluation

TBD

8/2008

 Slipped

Critical Change Report submitted Jan 31, 2009

IOC

TBD

9/2008

 Slipped

Critical Change Report submitted Jan 31, 2009

Increment: Air Force

 

 

 

 

Interface Requirements (Legacy) Complete

TBD

3/2008

 Slipped

Critical Change Report submitted Jan 31, 2009

System Integration Test

TBD

6/2008

 Slipped

Critical Change Report submitted Jan 31, 2009

System Acceptance Test

TBD

7/2008

 Slipped

Critical Change Report submitted Jan 31, 2009

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Increment: Marine Corps - Notional

 

 

 

 

Marine Corps Assessment

TBD

3/2008

 Slipped

Critical Change Report submitted Jan 31, 2009

DTS  Defense Travel System

 

 

 

 

Interface to Navy ERP

9/2007

10/2007

Met

 

Interface to GFEBS

10/2008

8/2008

Met

 

Implementation of Technical Refresh

5/2009

5/2008

 Slipped

Resources realigned from Special Circumstance Travel to test SPRs for Release 3 (Technical Refresh)

Interface to DEAMS

8/2009

8/2008

 Slipped

To align with the DEAMS release schedule, this task has been delayed

Compliance for Non-Transformational Systems

 

 

 

 

DCPS Legacy BEIS Interface

10/2009

10/2007

 Slipped

Due to reprogramming impacted by resource allocation

Acquisition Visibility

AV BTS AV Business Transformation Support

 

 

 

 

Increment: AV SOA Demo

 

 

 

 

Assign institutional responsibility for maintenance of the authoritative copy of each data element within component system(s)

10/2007

10/2007

Met

 

Develop technical interface standards

12/2007

12/2007

Met

 

WSLM issue data exchange standards and implementation schedule

12/2007

12/2007

Met

 

Specified MDAPS implement data exchange standards

1/2008

12/2007

Met

 

Query authoritative sources

1/2008

12/2007

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Increment: SAR-PB Reconciliation 

 

 

 

 

SAR submission in support of the FY10 budget contains explanations of principal differences between SAR values reported and the PB10 request

 

NA

 Deleted

Director, ARA, redirected the effort, making this milestone obsolete

MEVA (CAMS-ME) Military Equipment Valuation and Accountability

 

 

 

 

Increment: Increment 2

 

 

 

 

Item Unique Identification (IUID) Registry Interface to CAMS-ME

12/2007

12/2007

Met

 

CAMS-ME Increment 2A (Replace manual update of asset status, e.g., asset transfers, retirements, and loss data) CAMS-ME 2B (Replace manual update of asset additions) Program Review

11/2007

12/2007

Met

 

Spiral A IOC: Capital Asset Management System - Military Equipment (CAMS-ME)

1/2008

12/2007

Met

 

Navy Accountability Systems (Naval Vessel Registry (NVR) and Aircraft Inventory & Readiness Reporting Sys. (AIRRS)) Interface to IUID Registry Complete: Capital Asset Management System - Military Equipment (CAMS-ME)

12/2007

12/2007

Met

 

Acquisition Program Unique Identifier (APUID) Registry Interface to CAMS-ME

 

6/2008

 Deleted

ME selected to implement an end-to-end business process framework approach to identify gaps in the Services’ financial improvement plans. Updated to reflect changes in the current March 08 FIAR Plan

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Spiral B IOC: Capital Asset Management System - Military Equipment (CAMS-ME)

 

9/2008

 Deleted

ME selected to implement an end-to-end business process framework approach to identify gaps in the Services’ financial improvement plans. Updated to reflect changes in the current March 08 FIAR Plan

DAMIR  Defense Acquisition Management Information Retrieval

 

 

 

 

Service Components provide access to acquisition information directly from their Service Acquisition Information Systems via DAMIR web services rather than entering data into CARS

4/2008

1/2008

Met

 

FOC

4/2008

4/2008

Met

 

Retire CARS legacy system

5/2008

6/2008

Met

 

Common Supplier Engagement

eSRS  Electronic Subcontracting Reporting System

 

 

 

 

Initiate deployment of authoritative source for commercial supplier subcontracting reports within DoD

4/2008

4/2008

Met

 

FPDS-NG  Federal Procurement Data System-Next Generation

 

 

 

 

Initiate Development of the Verification and Validation plan for FPDS-NG

2/2008

3/2008

Met

 

PPIRS  Past Performance Information Retrieval System

 

 

 

 

Initiate deployment of PPIRS-SR with targeted list of Military Services and DLA

11/2008

9/2008

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

ASAS  Acquisition Spend Analysis Service 

 

 

 

 

Determine way ahead in accordance with the Defense Sourcing Portfolio

 

3/2008

 Deleted

System Deleted

DoD EMALL  DoD Electronic Mall

 

 

 

 

Increment: EMALL v8.1

 

 

 

 

Deploy next version including an improved customer care module and upgrade to current “pay.gov” requirements

1/2009

7/2008

 Slipped

Rebaselined due to delay in DISA readiness to accept DoD EMALL into the DISA DECC Ogden

JCCS Joint Contingency Contracting System

 

 

 

 

Increment: v.3.0 Release

 

 

 

 

Implement capability to modify TO/DO/calls

11/2007

NA

Met

 

Increment: v.3.5

 

 

 

 

Enhance capabilities in v3.0

2/2008

NA

Met

 

Implement multiple PR functionality and add contract line items

7/2008

NA

Met

 

SPOT Synchronized Pre-deployment and Operational Tracker

 

 

 

 

Implement Letter of Authorization capability

3/2008

3/2008

Met

 

SPS  Standard Procurement System

 

 

 

 

SPS FFMIA Compliance

 

9/2008

 Deleted

Based on the impending sunset (FY15) and decreasing development funding, SPS has been designated a SFIS Legacy Business Feeder System

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

SPS Target Accounting System Interface

 

9/2008

 Deleted

Based on the impending sunset (FY15)and decreasing development funding, SPS has been designated a SFIS Legacy Business Feeder System

Increment 2 (v4.2.2)

 

 

 

 

Delivery of Service Release 09

4/2008

NA

Met

 

Develop module to facilitate interoperability between Purchase Requests (PRs) from ERPs into SPS

8/2008

NA

Met

 

Deployment of SR08, which adds interfacing capabilities with CCR and addresses performance related and data integrity issues

11/2008

9/2008

Met

 

WAWF  Wide Area Workflow

 

 

 

 

WAWF FFMIA Compliance

9/2009

9/2008

 Slipped

IRB approved delayed SFIS compliance

WAWF Target Accounting System Interface

9/2009

9/2008

 Slipped

IRB approved delayed SFIS compliance

Increment: v.3.0.12 Release

 

 

 

 

Implement standard shipment and acceptance transaction processing

10/2007

10/2007

Met

 

Implement capability to process grants and cooperative agreements

10/2007

10/2007

Met

 

Increment v.4.0 Release

9/2008

9/2008

 

 

Implement standard invoicing and approval transaction processing - phase II

9/2008

9/2008

Met

 

Implement standard corrections processing

9/2008

9/2008

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Materiel Visibility

MV BTS MV Business Transformation Support

 

 

 

 

Complete system design of MAPAD repository Sep 07

10/2007

10/2007

Met

 

Complete full scale re-engineering DODAAD Repository Dec 07

12/2007

12/2007

Met

 

Complete MAPAD repository system development

5/2008

3/2008

Met

 

IUID Unique Item Identification Registry

 

 

 

 

All new Government Furnished Property (GFP) on solicitations and contracts meet the IUID requirements (requires DFARS change)

9/2009

10/2007

 Slipped

Rebaselined due to pub of FAR part 45 requiring DFAR case 2005-D015, Reports of government property to be rewritten

Phase II of marking and registering of legacy assets complete

3/2011

9/2008

 Slipped

The expected linkage from ECSS to the registry was not completed on time resulting in less than expected volume of the IUIDs

MILS to EDI or XML Transition from MILS to EDI or XML

 

 

 

 

Assess Jump Start funded systems ability to complete migration to high-priority DLMS transactions

10/2007

10/2007

Met

 

Assess DLMS migration via metrics reporting on a quarterly basis

10/2007

10/2007

Met

 

Component systems submit final nominations for FY08 Jump Start EDI migrations

10/2007

10/2007

Met

 

Evaluate and select successful system nominations for FY08 Jump Start EDI migration

1/2008

1/2008

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

All FY07 Jump Start funded systems complete migration to high-priority DLMS transactions

7/2008

3/2008

Met

 

RFID Radio Frequency Identification

 

 

 

 

Implement RFID at 3 aerial ports.

 

10/2007

 Admin
Correction

Replaced with equivalent milestone below with corrected finish date

Implement RFID at 3 aerial ports.

9/2008

12/2007

Met

 

Develop the DoD AIT implementation plan to serve as a roadmap for transitioning between the current AIT environment to the envisioned FY2015 environment outlined in the DoD AIT CONOPS

12/2007

12/2007

Met

 

Implement ability to read/write passive RFID at 25% of OCONUS DLA Distribution Centers.

12/2007

12/2007

Met

 

Implement ability to read/write passive RFID at 100% of all appropriate OCONUS DLA Distribution Centers.

9/2008

9/2008

Met

 

Publish DFARS clause requiring suppliers to apply passive RFID tags to shipments of all appropriate commodities to all locations to be instrumented

9/2009

12/2007

Slipped

The coordination with the medical community on possibly adding DoD medical locations to the DFARS clause has delayed the initiation of the rule making process. The delay allowed medical community, Navy, and other Components time to identify instrumented locations added into the DFARS clause.

Suppliers apply passive RFID tags to all shipments for all appropriate commodities to all locations to be instrumented.

 

2/2008

 Deleted

Contingent on pub DFARS clause date, which has been delayed.

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Real Property Accountability

EL Environmental Liabilities

 

 

 

 

Complete development of Department-wide EL reconciliation process and standards at the land parcel level

10/2008

3/2008

Met

 

HMPC&IMR Hazardous Materials Process Controls & Information Management Requirements

 

 

 

 

Establish Hazmat Configuration Support Panel

11/2007

11/2007

Met

 

Finalize Hazmat Component Implementation Plans

3/2008

3/2008

Met

 

Award contract for Hazmat MDC Part 2- Material Safety Data Sheets (MSDS)

3/2008

3/2008

Met

 

Complete final SLA for Hazmat Data Master

3/2008

3/2008

Met

 

Hazmat PHD regulatory reference data IOC available for linkage in the DLIS Data Master

9/2007

9/2008

Met

 

RPAR Real Property Acceptance Requirements

 

 

 

 

Issue draft Unified Facilities Criteria (UFC) 1-300-08 for coordination

9/2008

3/2008

Met

 

RPCIPR Real Property Construction in Progress Requirements

 

 

 

 

Incorporate and populate CIP data elements in authoritative systems - Army

9/2008

9/2008

Met

 

Implement sustainable CIP business processes - Army

9/2008

9/2008

Met

 

RPIR Real Property Inventory Requirements

 

 

 

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Increment: RPIR Implementation

 

 

 

 

Incorporate RPIR data elements in authoritative systems - Army

9/2009

NA

 Slipped

Completion date estimated re-established at Fiscal Year end

Incorporate RPIR Grant Specific real property data elements in authoritative systems - Navy-USMC (Group 4)

 

9/2008

 Deleted

Separate milestones by data element groupings no longer correspond to RPA’s method of oversight

Incorporate RPIR Core real property data elements in authoritative systems - Navy-USMC (Group 1)

 

9/2008

 Deleted

Separate milestones by data element groupings no longer correspond to RPA’s method of oversight

Incorporate RPIR Core real property data elements in authoritative systems - Army (Group 1)

 

9/2008

 Deleted

Separate milestones by data element groupings no longer correspond to RPA’s method of oversight

Incorporate RPIR Core real property data elements in authoritative systems Air Force (Group 1)

 

9/2008

 Deleted

Separate milestones by data element groupings no longer correspond to RPA’s method of oversight

Incorporate RPIR Financial real property data elements in authoritative systems
Navy-USMC (Group 2)

 

9/2008

 Deleted

Separate milestones by data element groupings no longer correspond to RPA’s method of oversight

Incorporate RPIR Financial real property data elements in authoritative systems - Army (Group 2)

 

9/2008

 Deleted

Separate milestones by data element groupings no longer correspond to RPA’s method of oversight

Incorporate RPIR Financial real property data elements in authoritative systems
Air Force (Group 2)

 

9/2008

 Deleted

Separate milestones by data element groupings no longer correspond to RPA’s method of oversight

Incorporate RPIR Grant Specific real property data elements in authoritative systems
Army (Group 4)

 

9/2008

 Deleted

Separate milestones by data element groupings no longer correspond to RPA’s method of oversight

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Incorporate RPIR Grant Specific real property data elements in authoritative systems 
Air Force (Group 4)

 

9/2008

 Deleted

Separate milestones by data element groupings no longer correspond to RPA’s method of oversight

Incorporate RPIR Linear Facilities real property data elements in authoritative systems
Army (Group 5)

 

9/2008

 Deleted

Separate milestones by data element groupings no longer correspond to RPA’s method of oversight

Increment: Defense Installation Spatial Data Infrastructure (DISDI)

 

 

 

 

Geo-enable Location Information

1/2008

1/2008

Met

 

Joint Installation Visualization Tool fully operational

1/2008

1/2008

Met

 

Strategic Installation Picture (SIP) IOC

9/2008

6/2008

Met

 

HMIRS Hazardous Materials Information Resource System

 

 

 

 

Test reference data from Master Data Capability

9/2008

12/2007

Met

 

Establish HMIRS - MDC interface requirements for discrete MSDS data

12/2008

9/2008

Met

 

KBCRS Knowledge Based Corporate Reporting System

 

 

 

 

Process preliminary FY07 Financial Liability data for Cleanup

 

10/2007

 Admin
Correction

Recurring operational activity

Process non-hazardous FY07 Solid Waste data into KBCRS

12/2007

12/2007

Met

 

Process FY07 Installation / Site data for Cleanup

 

3/2008

Admin
Correction

Recurring operational activity

Process FY07 Presidential Budget data for Cleanup

 

3/2008

Admin
Correction

Recurring operational activity

Process FY07 Green Procurement data into KBCRS

3/2008

3/2008

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Generate the detailed table data used for the Defense Environmental Programs Annual Report to Congress for FY07 Cleanup data

 

3/2008

Admin
Correction

Recurring operational activity

Update KBCRS Military Munitions Response Programs (MMRP) website with approved FY07 MMRP site list

 

3/2008

Admin
Correction

Recurring operational activity

Establish review and comment capabilities for MMRP sites for authorized users

 

3/2008

 Admin
Correction

Recurring operational activity

RPAD Real Property Assets Database

 

 

 

 

RPAD System initial operational capability (IOC)

10/2007

10/2007

Met

 

RPUIR Real Property Unique Identifier Registry

 

 

 

 

Asset Registry fully operational

12/2007

12/2007

Met

 

IOC for generic interface

6/2008

NA

Met

 

Incorporate Civil Works assets

6/2008

NA

Met

 

Site address data elements fully populated

6/2008

NA

Met

 

RPAD/RPUIR interface fully operational

9/2008

3/2008

Met

 

Financial Visibility

EFD Enterprise Funds Distribution (Initiative)

 

 

 

 

System Development and Demonstration

3/2008

3/2008

 Admin
Correction

Changed to two new milestones:
Release 1-Milestone C, and
Release 2-IOC

Award Contract

 

NA

 Admin
Correction

Contract award is assumed within the System Development and Demonstration phase

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

IGT/IVAN Intragovernmental Transactions/Intragovernmental Value Added Network

 

 

 

 

Determine preferred solution for Intragovernmental Transactions for reimbursables process

9/2008

11/2007

Met

 

SFIS  Standard Financial Information Structure

 

 

 

 

Develop cost-effective, Department-wide SFIS on-line training to drive change, increase awareness, and facilitate implementation

11/2007

12/2007

Met

 

Develop SFIS ERP standard configuration implementation guides

12/2007

12/2007

Met

 

Milestone 2 - Integrated Lines of Business into SFIS

1/2009

10/2007

 Slipped

A senior level group is defining the line of business structure. Waiting on standard values that will be defined by the IRG and approved by the DAWG. The SFIS Team did not receive info needed from the Line of Business Steward to complete the initiative

Increment: SFIS Compliance by System

 

 

 

 

REMIS SFIS Compliance

 

12/2007

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

REMIS FFMIA Compliance

 

6/2008

 Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

REMIS Target Accounting System Interface

 

12/2007

 Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

REMIS Legacy BEIS Interface

 

12/2007

 Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

SPS FFMIA Compliance

 

9/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

SPS Target Accounting System Interface

 

9/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

WAWF FFMIA Compliance

 

9/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

WAWF Target Accounting System Interface

 

9/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

DTS SFIS Compliance

 

9/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

DCPS Legacy BEIS Interface

 

10/2007

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

SDI FFMIA Compliance

 

6/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

EBM Legacy BEIS Interface

 

5/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

BSM-ENERGY SFIS Compliance

 

3/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

BSM-ENERGY FFMIA Compliance

 

3/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

BSM eProcurement Target Accounting System Interface

 

9/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

CFMS Target Accounting System Interface

 

6/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

MSC-FMS SFIS Compliance

 

8/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

Navy ERP FFMIA Compliance

 

4/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

Navy ERP Target Accounting System Interface

 

4/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

DPAS SFIS Compliance

 

3/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

EESOH-MIS SFIS Compliance

 

7/2008

Admin
Correction

Compliance milestones transferred to system owner for reporting purposes

BEIS  Business Enterprise Information Services

 

 

 

 

Transition CEFT to web services to support ERP’s (e.g.: GFEBS, DAI, DEAMS)

3/2008

NA

Met

 

SFIS-based Financial Reporting - Navy General Fund

6/2008

12/2007

Met

 

Milestone B Review by the Milestone Decision Authority

8/2008

6/2008

Met

 

SFIS-based Financial Reporting - Army General Fund

8/2008

6/2008

Met

 

Cash Accountability for GFEBS Implementation

10/2008

NA

Met

 

Cash Accountability for Financial Reporting in Support of DAI Implementation for BTA

10/2008

NA

Met

 

DoD Medical and Military Retirement

1/2008

NA

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Complete Requirements for Cash Accountability Reconciliation

TBD

3/2008

 Slipped

Awaiting review of approach by BTA and OSD. DFAS planned to support after current ERP release for Aug 30, 2008 - GFEBS, DAI, and DIMHRS. Will establish finish date when resolved

SFIS-based Financial Reporting - Army Working Capital Fund

TBD

6/2008

 Slipped

Waiting for OSD/DFAS approval of next priority after Army GF and Navy GF. Completion of task may change based on guidance received

Milestone B Review by the Milestone Decision Authority

 

12/2007

 Deleted

Task deleted when program changed strategy to pursue MS C exclusively. Currently, MDA has re-established a strategy to pursue MS B  listed below

Milestone C/Full Deployment Decision by the MDA

 

9/2008

 Deleted

BEIS strategically realigned into four primary business areas reporting to PEO FV which impacts acquisition strategy and schedule

Complete SFIS Compliant Financial Reporting for Defense Agencies

 

9/2008

 Deleted

Task deleted due to change in implementation. Decision made to reinstate milestone to align with DAI ERP rollout schedule. New milestone listed below

Subsume DCD/DCW, DDRS, and DCAS into BEIS

 

9/2008

 Deleted

BEIS Acquisition Strategy changed from System of Systems (SoS) to Family of Systems (FoS) rescinding the term/task “subsumed”

BEIS SFIS Compliance

9/2008

9/2008

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

BEIS FFMIA Compliance

4/2009

6/2008

 Slipped

OSD© claims ownership of FFMIA compliance for financial systems. Will be FFMIA compliant prior to BEIS program FDD scheduled for April 2009

BEIS Target Accounting System Interface

 

9/2008

 Deleted

Requirement captured under different investments (i.e.: Cash Accountability SFIS Compliance and Financial Reporting SFIS Compliance)

DCD/DCW Legacy BEIS Interface

 

9/2008

 Deleted

Compliance milestones transferred to system owner for reporting purposes

DAI Defense Agencies Initiative

 

 

 

 

BTA Pilot Go-Live

10/2008

6/2008

Met

 

Conference Room Pilot 2 (Core IOC functionality and common enterprise interfaces)

7/2008

NA

Met

 

Conference Room Pilot 1 (Core IOC functionality)

1/2008

NA

Met

 

Milestone B

3/2009

3/2008

 Slipped

Due to the rapid deployment of the program pilot, the program acquisition milestones are in the process of being updated to meet the new program schedule. March 2009 finish date is tentative

Blueprinting complete

 

3/2008

 Deleted

Additional Dev/Test milestones have been added to reflect accomplishments of Blueprinting

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

DAI SFIS Compliance

6/2008

6/2008

Met

 

DAI FFMIA Compliance

9/2010

8/2008

 Slipped

Due to delays in program execution, FFMIA will be achieved with completion of the Wave I agencies

Army

DLS  Distributed Learning System

 

 

 

 

Increment 4 - Deployed Digital Training Campus

 

 

 

 

DT&E

7/2008

12/2007

Met

 

OT&E

7/2009

2/2008

 Slipped

Slipped due to DISA Communications problems (SATCOM).

FRP

8/2009

7/2008

 Slipped

Slipped due to DISA Communications problems (SATCOM).

Milestone C

8/2009

7/2008

 Slipped

Slipped due to DISA Communications problems (SATCOM).

IOC

8/2009

8/2008

 Slipped

Slipped due to DISA Communications problems (SATCOM).

DTAS Deployed Theater Accountability System

 

 

 

 

Increment: DTAS v4.0 - Tracking Temporarily Attached & OPCON Personnel

 

 

 

 

DT&E

1/2008

10/2007

Met

 

System Qualification Testing

1/2008

10/2007

Met

 

User Acceptance Testing

1/2008

10/2007

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

FOC

 

2/2008

 Deleted

Fielding of DTAS version 3.3 being conducted by ARCENT C1 in theater, and it is estimated that all Army units in theater will be equipped (FOC) by June 2008

Increment: DTAS Theater 2

 

 

 

 

Development

4/2008

4/2008

Met

 

Field

 

7/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

FOC

 

8/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

eAWPS Enterprise Army Workload and Performance System

 

 

 

 

Increment: RMT

 

 

 

 

Integrate contract procurement with fund management

 

9/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Single host site provides data-centric capability

 

9/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Integrate RMT in the GFEBS design

 

9/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Transition RSW and IMCOM to RMT

 

9/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Develop RMT POI for Finance School/Army Logistic Management College (Manpower Course)

 

9/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Deployed standardized Funds Control, Budget Execution and Manpower functionality to all Army STANFINS sites

 

9/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Implement WMT and ATAAPS at IMA (key to LSS)

 

9/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Implement an integrated Purchase Request (PR) and Budget Tool

 

9/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Implement the Contractor Manpower Equivalent initiative

 

9/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Increment: WMT

 

 

 

 

IMA Beta Testing

10/2007

10/2007

Met

 

IOC Increment 1

1/2008

1/2008

Met

 

PMC & SPF Modules

2/2008

2/2008

Met

 

IOC Increment 2

 

4/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

IOC Increment 3

 

6/2008

 Deleted

Based on change in direction, milestones in this increment are deleted

Increment: EMDS

 

 

 

 

SI Contract Award/Kick-Off

10/2007

10/2007

Met

 

Critical Design Review

12/2007

12/2007

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Configuration/Testing Complete

2/2008

2/2008

Met

 

ATO/ATC or Equivalent Received

2/2008

2/2008

Met

 

Prototype Go-live

2/2008

2/2008

Met

 

Phase 1 - ETF/STF Complete

 

5/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Phase 1 - MTF/TTF Complete

 

5/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

StTF FRD

 

6/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

FY09 IRB Approval

 

8/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Critical Design Review

 

8/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

Program Assessment (M/S B)

 

8/2008

 Deleted

Based on change in direction, modules of this program have been reassigned to other functions

FBS  Future Business System

 

 

 

 

Increment: Program Initiation

 

 

 

 

Develop Reference Architecture

5/2008

5/2008

Met

 

Technology Prototyping and Component Integration Readiness and Benefits Assessments

5/2008

5/2008

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Evaluation of Candidate Applications

5/2008

5/2008

Met

 

Increment 1

 

 

 

 

Develop Increment 1 CDD

 

7/2008

 Deleted

Program is taking a different approach to providing necessary capabilities

Milestone B

 

7/2008

 Deleted

Program is taking a different approach to providing necessary capabilities

FCS-ACE  Future Combat Systems Advanced Collaborative Environment 

 

 

 

 

Identify FCS ACE technology transfer options to FBS

11/2007

11/2007

Met

 

Blockpoint 31: Major upgrade of core COTS product

12/2007

12/2007

Met

 

Blockpoint 32-34: Development and Deployment of capabilities to support FCS Spin Outs and Preliminary Design Review

 

9/2008

 Deleted

Program capability requirements led to clarification of Blockpoint releases. And this one milestone has been replaced with equivalent milestones, Blockpoint 32-33 and Blockpoints 34-36, both scheduled for a later fiscal year

GCSS-Army  Global Combat Support System - Army

 

 

 

 

Increment 1--Implement CDD Increment 1

 

 

 

 

Milestone B

7/2008

NA

Met

 

Segment 1 Operational Assessment

12/2007

NA

Met

 

GFEBS  General Fund Enterprise Business System

 

 

 

 

Milestone B

3/2008

10/2007

Met

 

Complete Release 1.2 Operational Assessment

12/2008

9/2008

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

PPB BOS  PPBE Business Operating System

 

 

 

 

Capability Package 1: PPB BOS Enterprise Foundation (Stability Operations)

2/2008

2/2008

Met

 

Capability Package 2: PPB BOS Engineering Guidance & Architecture

5/2008

5/2008

Met

 

PPBE BI/DW  PPBE Business Intelligence Data Warehouse

 

 

 

 

IOC

 

12/2007

 Deleted

System to be subsumed into PPB BOS

TC-AIMS II  Transportation Coordinators’ Automated Information for Movements System II

 

 

 

 

Increment: Block 3

 

 

 

 

FDDR

11/2007

11/2007

Met

 

IOC

1/2008

1/2008

Met

 

Compliance for Non-Transformational Systems

 

 

 

 

REMIS SFIS Compliance

12/2007

NA

Met

 

REMIS FFMIA Compliance

6/2008

NA

Met

 

REMIS Target Accounting System Interface

12/2007

NA

Met

 

REMIS Legacy BEIS Interface

12/2007

NA

Met

 

Navy

MC FII Marine Corps Financial Improvement Initiative

 

 

 

 

Increment: Discovery & Correction

 

 

 

 

FOC

9/2008

9/2008

Met

 

Increment: Audits

 

 

 

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Complete Validations, Assessments & Audits

9/2008

9/2008

Met

 

MSC-HRMS  Military Sealift Command Human Resources Management System

 

 

 

 

System Development

8/2008

9/2008

Met

 

Navy ERP Navy Enterprise Resource Planning

 

 

 

 

Retire SIGMA Pilot

12/2007

12/2007

Met

 

Retire CABRILLO Pilot

 

8/2008

Admin
Correction

Legacy system migration is not a milestone

Increment: Financial & Acquisition Release

 

 

 

 

IOC/Begin NAVAIR HQ Deployment

10/2007

10/2007

Met

 

Begin Echelon I Deployment

10/2007

10/2007

Met

 

Begin Air Warfare Center Deployments

10/2007

10/2007

Met

 

Begin SPAWAR Financials Deployment

10/2009

5/2008

 Slipped

The stabilization strategy for NAVAIR required the Navy ERP Program to reassign resources from SPAWAR to assist NAVAIR, thus delaying the SPAWAR deployment per ASN memo dated Mar 3, 2008

Increment: Wholesale and Retail Supply Release

 

 

 

 

Critical Design Review

8/2008

3/2008

Met

 

Test Readiness Review

2/2009

5/2008

 Slipped

ASNRDA Navy ERP Schedule change due per Mar 21, 2008 memorandum

Navy ERP FFMIA Compliance

4/2008

NA

Met

 

Navy ERP Target Accounting System Interface

4/2008

NA

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

One Supply One Supply

 

 

 

 

Determine Technical Solution

3/2008

3/2008

Met

 

Capability Assessment of Initial Single Sign On

5/2008

NA

Met

 

Achieve Approval to Operate (ATO)

 

NA

 Deleted

One Supply withdrew its application for C&A. The “Log Parts to Mission” functionality has been incorporated within MFOM, and MFOM has its own DADMS ID and ATO

TFSMS  Total Force Structure Management System

 

 

 

 

Block 2 CDD Final

9/2008

1/2008

Met

 

Fleet Rollout

1/2008

1/2008

Met

 

GFM DI  IOC

9/2008

4/2008

Met

 

Block 2 Milestone B

9/2009

9/2008

 Slipped

MCCDC CD&I schedule to deliver CDD in Sep 30, 2007 extended one year. Contractor took longer than expected to complete Block 1 Capability Production Document (CPD). Same contractor could not work to complete Block 2 CDD until CPD was done

IOC Block 2

12/2011

9/2008

Admin
Correction

Incorrect date originally provided. Block 2 IOC date is based on Block 2 Milestone C plus 15 months

MSC-FMS Compliance (Non-Transformational System)

 

 

 

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

MSC-FMS SFIS Compliance

5/2009

8/2008

 Slipped

Approx. 75% of SFIS data elements are mapped in the 11.5.10 DEV environment. Additional meeting between MSC and BTA required to clarify requirements for remaining SFIS data elements

Air Force

FM SDM  Financial Management Service Delivery Model

 

 

 

 

Financial Services Transformation: Stand-up Central Processing Center

10/2007

10/2007

Met

 

Enhanced Financial Advisor

9/2008

9/2008

Met

 

Center of Expertise FOC

9/2008

9/2008

Met

 

PSD Personnel Service Delivery

 

 

 

 

Increment: Personnel Services Center

 

 

 

 

EEO/MEO Tracking and Reporting Application

3/2009

NA

 Slipped

Original schedule date Jun 30, 2008. Deferred to a future spiral

Spiral 1, Block 20--Airmen Development Plan for Civilian, Role-based Access/E-viewer for Digitized Personnel Records

3/2009

12/2007

 Slipped

Spiral 1 - Delayed to explore Air Force (AF) enterprise roles-based access solution

Spiral 1, Block 40--ANG/Reserve FDTK

7/2009

2/2008

 Slipped

Delay result as effort placed on hold to explore AF enterprise roles-based access

Spiral 1, Block 50--WAPS Modernization

7/2009

7/2008

 Slipped

Block 50 will focus on DIMHRS interfaces. WAPS modernization will not take place in this block

Migration to DIMHRS IOC

10/2009

4/2008

 Slipped

Delayed as a result of DIMHRS slippage

Increment: Centralization of Total Force HR Services

 

 

 

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Centralizing HR processes currently performed at MAJCOMs

6/2009

NA

 Slipped

100 of 102 processes implemented. Business Process Owners still developing coordinated procedures for the field wrt NCO Academy management. Final process is civ ed/training.

(MIL; AD/RES/NGB) Centralizing HR transactional work currently performed at base-level

2/2009

4/2008

Slipped

Base Level Relocation (Assignments) under development by SPO

AFRISS  Air Force Recruiting Information Support System

 

 

 

FULLY IMPLEMENTED

Complete ANG functionality incl automated leads mgmt, in-service recruiting, enlisted professions, officer accessions, health professions, and electronic waiver processing

9/2008

6/2008

Met

 

FOC

9/2008

6/2008

Met

 

DEAMS-AF  Defense Enterprise Accounting and Management System - Air Force

 

 

 

 

Increment: Increment 2 USAF

 

 

 

 

Milestone A

6/2009

11/2007

 Slipped

Approval of the Analysis of Alternatives/Economic Analysis are in progress

Milestone B

11/2010

8/2008

 Slipped

Approval of the Analysis of Alternatives/Economic Analysis are in progress

EBS  Enterprise Business System

 

 

 

 

STES integration IOC

3/2008

NA

Met

 

FM/G2 re-hosting

11/2007

12/2007

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

GCSS-AF Level 3 Integration

 

NA

Admin
Correction

EBS is not an AF Enterprise system. Therefore GCSS-AF integration not required beyond Level 1

GCSS-AF Level 4 integration (hosted)

 

7/2008

 Admin
Correction

EBS is not an AF Enterprise system. Therefore GCSS-AF integration not required beyond Level 1

EESOH-MIS  Enterprise Environmental Safety and Occupational Health Management Information System

 

 

 

 

EESOH-MIS SFIS Compliance

TBD

7/2008

Slipped

This revised date is aligned with the current plan for EESOH-MIS to implement SFIS data elements

Increment: Version 1.3 (HazWaste)

 

 

 

 

V1.3 HazWaste Functionality

5/2008

11/2007

Met

 

Increment: Version 1.4 (Air) APIMS Rpl

 

 

 

 

Version 1.4.1 Air Functionality - Phase 1

 

9/2008

 Deleted

Increment replaced by revised Increment Version 1.4 Environmental Liabilities scheduled for completion in FY09

ETIMS  Enhanced Technical Information Management System 

 

 

 

 

Fielding Readiness Review (FRR)

2/2008

NA

Met

 

FIRST  Financial Information Resource System

 

 

 

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Milestone C

TBD

2/2008

 Slipped

Determination made that program did not provide the functional capabilities required. Working to determine a new date

DLA - Defense Logistics Agency

DLA EBS Enterprise Business System

 

 

 

 

BSM-Energy Business Systems Modernization - Energy

 

 

 

 

DLA EBS Initiatives-Continuous Post Product Improvement

3/2008

3/2008

 Met

 

FOC

3/2008

3/2008

Met

 

BSM-ENERGY SFIS Compliance

 

3/2008

 Deleted

DLA requested removal of these milestones in a letter submitted in  March, 2008

BSM-ENERGY FFMIA Compliance

 

3/2008

 Deleted

DLA requested removal of these milestones in a letter submitted in  March, 2008

Increment: OCONUS (Bulk & PC&S)

 

 

 

 

Full-Rate Production Decision Review (FRPDR)

12/2007

3/2008

Met

 

CFMS  Common Food Management System

 

 

 

 

Test Readiness Review

4/2008

2/2008

Met

 

Develop Class I Supply Chain Integration

 

4/2008

Admin
Correction

This milestone should not be included as it is synonymous with FOC and therefore duplicative.

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Milestone C

TBD

5/2008

 Slipped

CFMS systems integrator working to correct contract performance deficiencies. Upon correction of deficiencies, a new Milestone C date will be established.

CFMS Target Accounting System Interface

6/2008

NA

Met

 

USTRANSCOM

COP D2 Common Operational Picture for Distribution and Deployment

 

 

 

 

Spiral .5, Single Sign-on for NIPRNET

10/2007

10/2007

Met

 

DTTS/IRRIS Migration Effort - Merge Arms, Ammunition & Explosives Emergency Response IT Functionality into IRRIS IOC (Initial Tracking Capability)

10/2007

11/2007

Met

 

DTTS/IRRIS Migration Effort - Merge Arms, Ammunition & Explosives Emergency Response IT Functionality into IRRIS FOC

9/2008

8/2008

Met

 

DTCI Defense Transportation Coordination Initiative

 

 

 

 

Interim Authority to Operate

3/2008

12/2020

Met

 

First DLA Site Activations (Defense Distribution Center, Puget Sound, etc.)

5/2008

TBD

Met

 

First Service Site Activations (Navy)

10/2008

TBD

Met

 

FC Fusion Center

 

 

 

 

Stand-up the Air Refueling Management Branch in TCJ3 to globally manage Air refueling requirements and capacity

10/2007

10/2007

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Refine Fusion Center Orientation Course for use/deployment as needed

10/2007

10/2007

Met

 

Staff responses to Joint Staff DOTMLPF Change Request

 

10/2007

 Admin
Correction

Inaccurate Finish Date Replaced with equivalent milestone below

Bldg 1920 Contract Award (Dec 2007 - Award, Mar 2008 - Construction Start, Jul 2010 - Construction Complete)

2/2008

12/2007

Met

 

Initiate and complete combined DDOC floor and TCC business process reengineering

3/2008

3/2008

Met

 

JDPAC Joint Distribution Process Analysis Center

 

 

 

 

IOC - Analytic Product and Process Improvement Capability

9/2008

9/2008

Met

 

JTF-PO Joint Task Force-Port Opening

 

 

 

 

Work with JFCOM and Army to assign active duty personnel to USTRANSCOM for JTP-PO

7/2008

7/2008

Met

 

PMA Port Management Automation

 

 

 

 

Integration of WPS into GATES Initial Operational Capability (IOC)

11/2008

2/2008

Met

 

TDM Theater Distribution Management

 

 

 

 

CMOS operational from RAN providing access to TC-AIMS II Enterprise via Citrix

 

11/2007

Admin
Correction

Expending effort installing Citrix at the RAN was detracting from efforts towards the critical path, and had reached a point where success would give no improvement to the critical path

Deliver and conduct operational evaluation of CMOS client/server to Ft. Benning

 

12/2007

 Deleted

CMOS v8.0 development behind schedule, GFM used to facilitate DTCI fielding

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Deliver and conduct operational evaluation of CMOS client/server to Ft. Hood

3/2008

12/2007

Met

 

Deliver and conduct operational evaluation of CMOS client/server to Ft. Polk

2/2008

12/2007

Met

 

Deliver and conduct operational evaluation of CMOS client/server to Ft. Lewis

4/2008

12/2007

Met

 

Deliver and conduct operational evaluation of CMOS client/server to Ft. Dix

 

12/2007

 Deleted

CMOS v8.0 development behind schedule, GFM used to facilitate DTCI fielding

Deliver and conduct operational evaluation of CMOS client/server to 7 locations in the CONUS

 

12/2007

 Deleted

Milestone is redundant to individual CMOS Delivery milestones already in the plan

Development/Testing & Evaluation (DT&E) of CMOS 8.0 Web Version

 

3/2008

 Deleted

CMOS v8.0 development behind schedule, GFM used to facilitate DTCI fielding

Fielding of CMOS 8.0 Web Version

 

6/2008

 Deleted

CMOS v8.0 development behind schedule, GFM used to facilitate DTCI fielding

AT21 Agile Transportation for the 21st Century

 

 

 

 

Contract award for new acquisition

TBD

11/2007

 Slipped

USTRANSCOM Chief of Staff made the decision NOT to award contract due to affordability issues (Mar 7, 2008)

CPA  Customs Process Automation

 

 

 

 

FOC (Increment 1) - Field & operation of Automated Customs Processing in 2 countries

3/2009

NA

 Slipped

Finish date (Nov 28, 2008) was delayed due to additional security requirements directed by DISA for the system to be installed

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

FOC (Increment 1) - Field & operation of Automated Customs Processing in 4 countries.

 

6/2008

Admin
Correction

Deleted because of inaccurate Finish Date reported at 2007 ETP publication. Replaced with equivalent milestone

DEAMS  Defense Enterprise Accounting and Management System

 

 

 

 

Increment: Increment 1 USTRANSCOM

 

 

 

 

Complete Spiral 1 (Commitment Accounting) deployment at Scott AFB

6/2008

NA

Met

 

Complete Spiral 2 functional and technical design (core accounting functionality)

7/2008

NA

Met

 

DPS Defense Personal Property System

 

 

 

 

DPS Initial Operational Capability (IOC)

11/2007

3/2008

Met

 

DPS rollout to 18 sites

11/2008

9/2008

Met

 

IGC Integrated Data Environment (IDE) / Global Transportation Network (GTN) Convergence

 

 

 

 

IGC Contract Award

6/2008

9/2008

Met

 

DFAS - Defense Finance & Accounting Service

DFAS BTS  DFAS Business Transformation Support

 

 

 

 

Complete MPIAP systems changes for DJMS-AC and DJMS-RC

7/2008

6/2008

Met

 

Complete review of the Military Pay Compensation system to simplify pay

3/2009

9/2008

 Slipped

Completed - changes have been identified and implemented - now focusing on DIMHRS

Deploy DDS v4.0 to integrate and share common data with Treasury and improve GWOT cash-handling processes

9/2008

9/2008

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Close DFAS sites under BRAC per FY08 schedule

9/2008

9/2008

Met

 

BAM Implementation

12/2008

6/2008

Met

 

Increment: Increased Business Intelligence Capabilities

 

 

 

 

Develop MyMetrics Executive Dashboard

9/2008

3/2008

Met

 

EC/EDI  Electronic Commerce/Electronic Data Interchange

 

 

 

 

Increment: Increased Business Intelligence Capabilities

 

 

 

 

Expand EC capability to include WAWF miscellaneous payments

4/2008

NA

Met

 

Modify IAPS to provide Powertrack functionality

11/2008

1/2008

Met

 

SDI (ADS) Standard Disbursing Initiative

 

 

 

 

SDI SFIS Compliance

4/2008

NA

Met

 

Increment: Eliminate SRD I  

 

 

 

 

Convert SRD I to ADS (DFAS Columbus)

 

9/2008

 Deleted

SDI is being re-baselined to focus on ERPs

Convert SRD I to ADS (DFAS Indianapolis)

 

9/2008

 Deleted

SDI is being re-baselined to focus on ERPs

ADS FOC

 

9/2008

 Deleted

SDI is being re-baselined to focus on ERPs

Increment: Reduce Number of Disbursing Service Sites

 

 

 

 

FOC

 

9/2008

 Deleted

SDI is being re-baselined to focus on ERPs

MHS - Medical Health Systems

JEHRI Joint Electronic Health Record Interoperability

 

 

 

 

Implement BHIE Theater data

10/2007

12/2007

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Implement CHDR-BHIE Interface, Release 2

12/2007

12/2007

Met

 

Define Department unique and joint inpatient EHR functional requirements for a potential joint application

1/2008

NA

Met

 

Begin Development of Business Processes, Business Rules, and Requirements Validation to Automate Activation of Active Dual Consumer Patients

2/2008

NA

Met

 

Implement CHDR-BHIE Interface, Release 3

6/2008

6/2008

Met

 

Provide report on the Analysis of Alternatives and recommendations for the Joint DoD/VA Inpatient Electronic Health Record

9/2008

9/2008

Met

 

Implement the ability to share viewable family history/social history/ other history, questionnaires and forms

9/2008

9/2008

Met

 

Implement automated activation of Active Dual Consumer patient capability

9/2008

9/2008

Met

 

Continue work to ensure VA patients treated in DoD facilities have DoD Electronic Data Interchange Person Numbers (EDI PN IDs) to facilitate matching patients and sharing electronic health information on shared patients

9/2008

NA

Met

 

Implement CHDR Phase 2, Release 2,  Part of 2nd phase of JEHRI implementation (Laboratory Results)

10/2009

9/2008

Slipped

DoD on track, VA delay; this goal has been moved to Oct 2009 in the 2009-2011 Draft JSP (not yet signed)

AHLTA

 

 

 

 

Increment: Block I Enhancements

 

 

 

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Begin deployment of the first two increments of DFI Enabled AHLTA, as part of AHLTA v3.4

 

9/2008

Deleted

Release 1.1 delivered to Government, but direction is changing; new milestone recommended to capture phase 1 of HAIMS

Complete requirements decomposition, design, coding and developer testing and deliver the functionality of HART Phase I to the Government for DT&E

12/2008

9/2008

Met

 

Complete requirements decomposition, design, coding and developer testing and deliver Increment 3 of DFI Enabled AHLTA to the Government for DT&E

 

9/2008

Deleted

Project direction being revised; new milestone recommended to capture phase 1 of HAIMS

Increment: Block II

 

 

 

 

Validate that any AHLTA infrastructure or applications gaps identified during OT&E in anticipation of deployment in the next FY have been resolved

12/2008

9/2008

Met

 

Increment: Block III

 

 

 

 

Milestone B

 

1/2008

Deleted

Project direction being revised

DMLSS  Defense Medical Logistics Standard System

 

 

 

 

Increment: Transition the JMAR application from an operational data store (ODS) to a data warehouse (DW):

 

 

 

 

Deploy new front end (user interface) to support Data Warehouse beginning with the Blood Module

11/2007

12/2007

Met

 

Model, Build and Load Complete Data Warehouse including the Inventory, Assemblage, Health Affairs, Equipment and Item Receipt Modules

9/2008

6/2008

Met

 

Complete testing and fielding of JMAR Data Warehouse

10/2008

9/2008

Met

 

 

Task Name

Revised Finish

FY08 Baseline Finish Date

Status

Explanation

Increment: Implement RFID capability in the DMLSS system along with new medical logistics business processes that will result in compliance with DoD policy mandating the capability of Radio Frequency Identification (RFID) for processing materiel receipts:

 

 

 

 

Complete RFID capability coding development within the DMLSS system and complete development testing

3/2008

12/2007

Met

 

Conduct formal operational testing with the medical materiel Prime Vendor Owens & Minor by processing Electronic Data Interchange (EDI) transactions from the vendor to the DMLSS test environment

6/2008

3/2008

Met

 

Deploy RFID as a capability within the DMLSS system as well as the hardware infrastructure to alpha test sites at Ft. Belvoir, Bethesda Naval Medical Center, and Dover AFB

6/2009

6/2008

Slipped

DMLSS v3.1 with RFID deployed to Ft. Belvoir site. DMLSS v3.1 without RFID turn on deployed to Bethesda site since Navy Certificate Of Net-worthiness denied authority to test RFID. DMLSS v3.1 not deployed to Dover site since AF unwilling to provided Authorization

Analyze RFID deployment and effectiveness of business processes at Alpha sites

3/2009

9/2008

Slipped

Analysis of Ft. Belvoir site is ongoing